HHRM recently
commissioned another concrete batching plant in Ras Zuwayed, in the Southern
region of Bahrain. The additional concrete plant was established to serve the
increasing concrete demand for Alba Line 6 Project, BAPCO Modernization
Project, King Abdulla Medical City Project and other housing projects in that
area.
The first plant
in Ras Zuwayed factory was erected on 2014 with capacity of 2000 m³ per day
mainly to serve the southern governorate housing project.
With the advent
of this new concrete plant, HHRM Ras Zuwayed factory boast a production
capacity of around 3000 m³ per day.
The plant
utilizes the latest technology using a fully computerized automatic control
system known as Command Alkon. The operating systems are continually updated in
line with ever-changing technology upgrades.
|